Question # 124

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

Options:

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Buy Now
Question # 125

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the ‘business case' practice when the project board undertakes this review?

Options:

A.

Manage by exception

B.

Manage by stages

C.

Focus on products

D.

Tailor to suit the project

Buy Now
Question # 126

Which term is defined as the means by which an organization transitions to a desired future state?

Options:

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Buy Now
Question # 127

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Question # 128

How is Uncertainty Identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Question # 129

Which statement BEST describes how approved plans enable control?

Options:

A.

By defining the quality specifications of individual products in product descriptions

B.

By enabling the controlled consideration of business opportunities

C.

By defining the benefits that need to be realized through the benefits management approach

D.

By defining what is within the approved project scope to avoid scope creep

Buy Now
Question # 130

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Buy Now
Question # 131

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

Options:

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

Buy Now
Question # 132

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

Options:

A.

Manage by exception

B.

Manage by stages

C.

Ensure continued business Justification

D.

Focus on products

Buy Now
Question # 133

Which is a feature of PRINCE2?

Options:

A.

It is naturally right=sized to the scale of every project

B.

It promotes improving processes for every project

C.

It replaces the need to apply specialist Industry-specific lifecycles

D.

It focuses on completing the project on time as its main objective

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Feb 23, 2025
Questions: 461
Prince2-Foundation pdf

Prince2-Foundation PDF

$25.5  $84.99
Prince2-Foundation Engine

Prince2-Foundation Testing Engine

$28.5  $94.99
Prince2-Foundation PDF + Engine

Prince2-Foundation PDF + Testing Engine

$40.5  $134.99