What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Which member of the project management team should secure funding for the project before the project stars?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
The project manager needs to confirm that operational teams are responsible for the running of the outputs.
During which step of the ‘organizational design and development’ technique should the project manager ensure this?