Question # 94

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Question # 95

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options:

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Buy Now
Question # 96

Which is NOT one of the PRINCE2 integrated elements?

Options:

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Buy Now
Question # 97

Which statement defines a risk?

Options:

A.

A certain event occurring in the future that will have a negative impact on the project's objectives

B.

An event that has already occurred that the Project Manager must deal with immediately

C.

An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

D.

An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Buy Now
Question # 98

Which is a difference between management and technical stages?

Options:

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Buy Now
Question # 99

Which is a typical core activity within configuration management?

Options:

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Buy Now
Question # 100

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Buy Now
Question # 101

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Question # 102

Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

Options:

A.

Avoid

B.

Reduce

C.

Share

D.

Transfer

Buy Now
Question # 103

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

Options:

A.

Management strategies

B.

Plan

C.

Stakeholder interests

D.

Time-driven controls

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Feb 23, 2025
Questions: 461
Prince2-Foundation pdf

Prince2-Foundation PDF

$25.5  $84.99
Prince2-Foundation Engine

Prince2-Foundation Testing Engine

$28.5  $94.99
Prince2-Foundation PDF + Engine

Prince2-Foundation PDF + Testing Engine

$40.5  $134.99