Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.