According to PRINCE2, which characteristic is necessary for an effective project board?
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?