The purpose of the quality theme in PRINCE2® is to define and implement the means by which the project will ensure that all products are fit for purpose and meet their requirements. This theme is essential for planning, designing, developing, and delivering products that satisfy the customer's expectations and standards defined for the project.References: = PRINCE2® 7 Foundation handbook and online resources
Question # 35
Whitt is 3 purpose of the initiating a project’ process?
Options:
A.
To prepare the contract for the project to enable the project board to commit to delivery
B.
To provide the project board with Just Enough Information to decide whether to approve the Initiation stage
C.
To provide the opportunity for the senior user in confirm that they find the project product acceptable
D.
To enable the project board to empower the project manager to work within delegated authority limits
The purpose of the 'Initiating a Project' process is to provide the Project Board with just enough information to decide whether to approve the initiation stage. This process involves the development of a more detailed Business Case and Project Plan, which are crucial for the Project Board to assess the project's viability and decide on its initiation confidently. References: PRINCE2® official guide and syllabus.
Question # 36
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
Options:
A.
By providing a common understanding of the products required
B.
By providing the tolerances for the project manager’s objectives
C.
By providing roles descriptions for the project management team
Applying the ‘focus on products’ principle in PRINCE2® helps to ensure stakeholder expectations are met by providing a common understanding of the project’s products. This principle emphasizes the importance of clearly defining what the project has to deliver, in terms of both scope and quality, so that there is no ambiguity about the expected deliverables, thereby aligning expectations and project outputs.References: = PRINCE2® 7 Foundation handbook and online resources
Question # 37
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
Options:
A.
when a stage plan has been prepared for
B.
at the beginning of
C.
when all the delivery steps have been completed within
The "Managing a Stage Boundary" process in PRINCE2® should be executed at, or close to the end of, a management stage. This timing allows for proper assessment of the stage's outcomes and preparation for the next stage, ensuring effective planning and reporting as required by the project board. References: PRINCE2® Foundation Handbook, Managing a Stage Boundary section.
Question # 38
Which is a minimum requirement for applying the organization theme?
Options:
A.
To document the project management team structure
B.
To define the experience required for each project role
C.
To include external stakeholders on the project board
D.
To train project team members in the use of PRINCE2
A minimum requirement for applying the Organization Theme in PRINCE2 is to document the project management team structure. This documentation includes defining the roles and responsibilities of each team member, facilitating clear communication and effective management throughout the project lifecycle. References: PRINCE2® 7 Foundation Handbook and official training materials.
A risk budget may fund the implementation of a fallback plan, which is activated if a risk materializes. This ensures that resources are available to manage and mitigate the impact of risks on the project, aligning with proactive risk management strategies in PRINCE2. References: PRINCE2® 7 Foundation Handbook and official training materials.
Question # 40
Which is an objective of the Starting up a Project process?
Options:
A.
Identify who will be responsible for creating the Project Plan
B.
Agree how the project will be monitored and controlled after initiation
C.
Authorize the Project Manager to proceed with the initiation stage
D.
Agree how issues and changes will be identified, assessed and controlled
The objective of the Starting up a Project process in PRINCE2 includes ensuring that the roles and responsibilities are defined before the project is formally initiated. This includes identifying who will be responsible for creating the Project Plan. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.
Question # 41
Which is created during the Starting up a Project process?
During the Starting up a Project process, one of the key activities is to create role descriptions for the project management team. This ensures that everyone involved understands their responsibilities and the expectations placed upon them before the project commences. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.
Question # 42
What is the project manager role responsible for?
Options:
A.
Approving the completion of each management stage
B.
Ensuring that the project produces the required products
The Project Manager role in PRINCE2 is primarily responsible for ensuring that the project produces the required products, to the defined standards of quality and within the specified constraints of time and cost. This central responsibility involves coordinating all project activities and resources to achieve the project objectives.References: PRINCE2® 7 Foundation resources and materials.
Question # 43
Which is a purpose of the Risk Register?
Options:
A.
Describe the risk management techniques and standards to be applied to the project
B.
Act as a central record of information relating to the identified risks for the project
C.
Act as a repository for informal issues
D.
List the responsibilities for achieving an effective risk management procedure
The purpose of the Risk Register in PRINCE2® is to act as a central record of information relating to the identified risks for the project. It includes details about each risk such as their description, probability, impact, and countermeasures. The register helps in monitoring and controlling risks efficiently throughout the project lifecycle.References: PRINCE2® 7 Foundation handbook and documents.