Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

Prince2-Foundation Exam Dumps - PRINCE2 Certification Questions and Answers

Question # 14

Which process is used by the project board to respond to on exception report?

Options:

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Buy Now
Question # 15

Which is 3 purpose of the ‘plans! practice?

Options:

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Buy Now
Question # 16

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

Options:

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Buy Now
Question # 17

How are team managers involved in tailoring PRINCE2 suit the project?

Options:

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Buy Now
Question # 18

What must be done for a project to be a PRINCE2 project?

Options:

A.

The project must form part of a programme or portfolio

B.

The project must meet the minimum requirements for applying the themes

C.

The project must use the recommended approach to planning

D.

The project roles must be combined wherever possible

Buy Now
Question # 19

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?

Options:

A.

Business case

B.

Plans

C.

Change

D.

Progress

Buy Now
Question # 20

Which statement about project roles is CORRECT?

Options:

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Buy Now
Question # 21

How can the risk culture of 3n organization make decision-making less effective?

Options:

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk

Buy Now
Question # 22

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Buy Now
Question # 23

What is the change authority role permitted to authorize?

Options:

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Feb 23, 2025
Questions: 461
Prince2-Foundation pdf

Prince2-Foundation PDF

$25.5  $84.99
Prince2-Foundation Engine

Prince2-Foundation Testing Engine

$28.5  $94.99
Prince2-Foundation PDF + Engine

Prince2-Foundation PDF + Testing Engine

$40.5  $134.99