How does the project board use the 'manage by stages' principle to control the project?
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
What must be produced to meet the minimum requirements for applying the change theme?
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products