Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

ISTQB-CTFL Exam Dumps - ISTQB Foundation Level Questions and Answers

Question # 64

The whole-team approach:

Options:

A.

promotes the idea that all team members should have a thorough understanding of test techniques

B.

is a consensus-based approach that engages the whole team in estimating the user stories

C.

promotes the idea that all team members should be responsible for the quality of the product

D.

is mostly adopted in projects aimed at developing safety-critical systems, as it ensures the highest level of testing independence

Buy Now
Question # 65

In maintenance testing, what is the relationship between impact analysis and regression testing?

Options:

A.

Impact analysis requires a regression testing for only the tests that have detected faults in previous SW release

B.

There is no relationship between impact analysis and regression testing.

C.

Impact analysis requires a regression testing for all program elements which were newly integrated (new functionalities).

D.

The impact analysis is used to evaluate the amount of regression testing to be performed.

Buy Now
Question # 66

For withdrawing money tram an Automated Teller Machine (ATM), the following conditions are required:

- The bank card is valid

- The PIN code is correct

- Money is available in the user's account

The following are some possible interactions between the user and the ATM:

- The entered card is invalid The card is rejected

- The PIN code is wrong The ATM asks for another PIN code

- The requested amount is more than available in the user's account: The ATM asks for another amount

- The requested amount is available in the user's account The ATM dispenses the money

Which test design technique should be used to cover all possible combinations of the in put conditions?

Options:

A.

Use case based testing

B.

Decision table

C.

Boundary value analysis

D.

Equivalence class partitioning

Buy Now
Question # 67

Given the following review process main activities and specific review activities:

a.Planning

b.Initiate review

c.Issue communication and analysis

d.Fixing and reporting

1.Creating defect reports

2.Estimating effort and timeframe

3.Recording updated status of defects

4.Selecting the people to participate

5.Distributing the work product and other material

6.Evaluating the review findings

Which of the following BEST matches the review process main activities with the appropriate specific review activities?

Options:

A.

2-a, 4-a, 5-b, 6-c, 1-d, 3-d

B.

2-a, 5-a, 1-b, 4-b, 3-c, 6-d

C.

1-a, 4-b, 5-b, 6-c, 2-d, 3-d

D.

2-a, 4-b, 5-c, 1-d. 3-d, 6-d

Buy Now
Question # 68

Consider the following examples of risks identified in different software development projects

[1]. It may not be possible to generate the expected workloads to run performance tests, due to the poor hardware equipment of the machines (load injectors) that should generate these workloads.

[ii]. A user's session on a web application is not invalidated after a certain period of inactivity (configured by the system administrator) of the user,

[iii]. The test team will not have an adequate requirements specification (since many requirements will still be missing) by the time test design and analysis activities should begin according to the test plan.

[IV]. Following a failure, the system is unable to continue to maintain its pre-failure operation and some data becomes corrupted.

Which of the following statements is TRUE?

Options:

A.

[ii] and [IV] are product risks; [i] and [iii] are project risks

B.

[ii]and [iii] are product risks. [I] and [IV] are project risks.

C.

[i], and [iV] are product risks; [ii] and [iii] are project risks

D.

[i], [II] and [iii] are product risks, [IV] is a project risk.

Buy Now
Question # 69

Which test approach will best fit a new project, with little documentation and high probability for bugs?

Options:

A.

Exploratory testing

B.

Requirements based testing

C.

Metric based approach

D.

Regression testing

Buy Now
Question # 70

Match each objective to the correct test level

Objective:

A)Verifying whetherthe functionalandnon-functlonalbehaviorsof the system are as designed andspecified.

B)Verifying whetherthe functionalandnon-functlonalbehaviorsof the interfaces are as designed.

C)Verifying whetherthe functionalandnon-functionalbehaviorsof the components are as designedand specified.

D)Establishing confidence in the quality of the systemas a whole.

Test Level:

1.Component testing.

2.Integration testing.

3.System testing.

4.Acceptance testing.

Options:

A.

A3, B2. C4. D1

B.

A2, B3, Cl, D4

C.

A3. B2. C1. D4

Buy Now
Question # 71

Which of the following would be the LEAST likely to be used as the basis for a test exit criteria?

Options:

A.

Test schedules

B.

Cost of testing performed so far

C.

Confidence of testers in tested code

D.

Number of unfixed defects

Buy Now
Question # 72

In the newest version of payroll system number of changes were made. As a tester you got a task to perform regression and confirmation tests. Which of the following project activities are related to confirmation testing?

Options:

A.

Testing due to the application of a new version of the interface

B.

Testing that fixes resolved the defects in the search function

C.

Testing if a system still works after update of an operating system

D.

Testing to ensure the adding of a new functionalities haven't broken existing functions

Buy Now
Question # 73

For each of the test cases to be executed, the following table specifies the priority order and dependencies on other test cases

Which of the following test execution schedules is compatible with the logical dependencies and allows executing the test cases in priority order?

Options:

A.

TC4, TC3, TC2, TC6, TC5. TC1

B.

TC4, TC6, TC3, TC2, TC5, TC1

C.

TC3, TC5, TC6, TC1, TC4, TC3

D.

TC4, TC3, TC2, TC6, TC1, TC5

Buy Now
Exam Code: ISTQB-CTFL
Exam Name: ISTQB Certified Tester Foundation Level (CTFL) v4.0
Last Update: Feb 23, 2025
Questions: 288
ISTQB-CTFL pdf

ISTQB-CTFL PDF

$25.5  $84.99
ISTQB-CTFL Engine

ISTQB-CTFL Testing Engine

$28.5  $94.99
ISTQB-CTFL PDF + Engine

ISTQB-CTFL PDF + Testing Engine

$40.5  $134.99