Question # 124

A certain stakeholder requirement has been analyzed and broken down into several solution requirements, each affecting a different IT system. After solution design, the business analyst (BA) receives feedback that

one of the IT systems will take longer than anticipated to implement. What requirements artifact or technique will assist the BA in better understanding the related requirements?

Options:

A.

MoSCoW prioritization

B.

Backlog management

C.

Requirements documentation

D.

Traceability matrix

Buy Now
Question # 125

A company wants to increase its market share in the industry and its Board has prioritized capabilities that need to be implemented to achieve the goal. The business requirements for the top priority were signed off and the solution design has been completed. Due to technical constraints, it is not feasible to implement all the requirements at the same time. What must the business analyst (BA) do to deal with this situation?

Options:

A.

Redefine the business requirements associated with each implementation

B.

Recommend a reduction in the project scope

C.

Allocate requirements to different releases

D.

Ensure all requirements are traceable using a matrix

Buy Now
Question # 126

Verification of requirements on the projects have highlighted an issue regarding misunderstanding of design models among key stakeholders. A major reason cited for the misunderstanding was the technical jargon and models used in the documentation. What must the business analyst (BA) do to improve the understanding?

Options:

A.

Ensure completeness within the models used

B.

Verify that elements within the models are used consistently

C.

Represent design models using common terminology

D.

Check for compliance with organization standards

Buy Now
Question # 127

A business analyst (BA) worked with two stakeholders to finalize the access rights related requirements for an internal software application. According to the first stakeholder “Comments, once entered in the application, should be stored for 365 days and should not allow the users to delete”. According to the second stakeholder, “The users with super administrator privileges should be able to add/delete/modify every page/section in the entire application.” Which characteristic does this pair of requirements fail to meet?

Options:

A.

Concise

B.

Consistent

C.

Complete

D.

Complex

Buy Now
Question # 128

A business analyst (BA) is validating requirements and has found that the design cannot be validated to support the requirements. Which of the following is creating this situation?

Options:

A.

Incorrect assumptions.

B.

Lack of requirements traceability.

C.

Missing requirements.

D.

Substandard solution design.

Buy Now
Question # 129

Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second BA. The other BA explains that these details, along with several other items mentioned in the checklist, are required to:

Options:

A.

select elicitation techniques.

B.

prepare stakeholders.

C.

secure supporting material.

D.

understand scope of elicitation.

Buy Now
Question # 130

A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal. Which of the following would the BA classify as a project risk?

Options:

A.

Customer service ratings will increase with the new system

B.

Current infrastructure may not support increased performance

C.

Expenditures are currently below budgeted estimates

D.

Support calls will increase if the change is not performed

Buy Now
Question # 131

A banking giant recently found a major security loophole in their online banking platform that could expose customer information. Security experts and the business analyst (BA) develop a low cost, low effort emergency fix to address this issue. What factor should the BA use to convince the bank to move forward with the emergency fix?

Options:

A.

Cost

B.

Schedule

C.

Impact

D.

Urgency

Buy Now
Question # 132

A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project. What is the main purpose of the BA performing this work?

Options:

A.

To establish the key performance indicators

B.

To define the future state

C.

To identify the domain subject matter expert

D.

To document the current state

Buy Now
Question # 133

Performance measures have been collected and analyzed by a business analyst (BA) to evaluate a solution that was launched a few years ago; however, the performance measures do not indicate whether or not the solution is contributing to the desired value. What is the recommended next step?

Options:

A.

Replace the solution as soon as possible

B.

Identify and collect more measurements

C.

Increase the efficiency of the solution

D.

Reduce the business' expectations of value

Buy Now
Question # 134

A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?

Options:

A.

Repository

B.

Document management

C.

Email

D.

Individual collaboration

Buy Now
Question # 135

A business analyst (BA) is working on a complex project involving many stakeholders for which the business case has been previously completed and signed off. After an organizational restructure, new stakeholders have been assigned to the project working group, but do not see the value in the project outcomes and refuse to collaborate. What is a guideline or tool the BA can use to focus stakeholders on a common goal?

Options:

A.

A business requirements document

B.

An alternate stakeholder plan

C.

A stakeholder matrix

D.

A future state description

Buy Now
Question # 136

A business analyst (BA) must model information characteristics across multiple information systems for a project. What type of model captures this information?

Options:

A.

Interface analysis

B.

Business capability analysis

C.

Decision analysis

D.

Force field analysis

Buy Now
Question # 137

The business analyst (BA) has documented the requirements for a new system and is preparing the requirements for approval. Which of the following helps ensure that requirements are fully understood and traceable?

Options:

A.

Requirements are extracted for review

B.

Requirements are properly classified

C.

Requirements are validated

D.

Requirements meet regulatory standards

Buy Now
Question # 138

A business analyst (BA) is creating a business process model (BPM) showing how the organization will handle errors reported on its website. The BA held a workshop with stakeholders about how the process might work. The BA was also given an instruction manual about a similar error-handling situation, but was advised that some minor aspects are not applicable to the new process. How can the BA use the manual?

Options:

A.

Ignore the manual's information when creating the BPM since it is about a different situation

B.

Identify the discrepancies in process between the manual and the workshop results and resolve these with stakeholders

C.

Create a new version of the manual based on the original

D.

Rely on the manual to create the BPM and ignore the interview results because no single stakeholder has the whole picture of the process

Buy Now
Exam Code: CCBA
Exam Name: Certification of Capability in Business Analysis (CCBA)
Last Update: Apr 1, 2025
Questions: 638
CCBA pdf

CCBA PDF

$25.5  $84.99
CCBA Engine

CCBA Testing Engine

$28.5  $94.99
CCBA PDF + Engine

CCBA PDF + Testing Engine

$40.5  $134.99