CCBA Exam Dumps - IIBA Certification of Capability in Business Analysis Questions and Answers

Question # 64

A business analyst (BA) is working on a project that follows incremental and iterative approaches. The BA and the stakeholders have shortlisted several user stories to be considered in the project scope. Which of the following methods would enable them to arrive at a common understanding on delivering value in the product and ranking the stories?

Options:

A.

Story decomposition

B.

State modelling

C.

Value stream mapping

D.

MoSCoW prioritization

Buy Now
Question # 65

A business analyst (BA) is planning to elicit requirements. The BA understands the scope of the elicitation and has selected interviewing as an appropriate technique. Which of the following is part of the logistics for these interviews?

Options:

A.

Relationships between elicited requirements

B.

Performance metrics

C.

Definition of the future state

D.

Participants and their roles

Buy Now
Question # 66

A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?

Options:

A.

Repository

B.

Document management

C.

Email

D.

Individual collaboration

Buy Now
Question # 67

The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system. Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:

Options:

A.

show all of the decision points in the business process.

B.

illustrate the relationships between relevant requirements.

C.

capture all users that will be impacted by the project.

D.

detail the inner workings of the system being changed.

Buy Now
Question # 68

Verification of requirements on the projects have highlighted an issue regarding misunderstanding of design models among key stakeholders. A major reason cited for the misunderstanding was the technical jargon and models used in the documentation. What must the business analyst (BA) do to improve the understanding?

Options:

A.

Ensure completeness within the models used

B.

Verify that elements within the models are used consistently

C.

Represent design models using common terminology

D.

Check for compliance with organization standards

Buy Now
Question # 69

During the analysis, synthesis, and refinement of elicitation results the business analyst (BA) has discovered that some information is missing. Which course of action would resolve the situation?

Options:

A.

Verify the requirements results

B.

Conduct elicitation activities

C.

Conduct traceability analysis

D.

Validate the requirements

Buy Now
Question # 70

A business analyst (BA) needs to obtain agreement on and approval of requirements for a software solution. In order for this task to proceed, what does the BA need to understand?

Options:

A.

The verified requirements

B.

The solution design

C.

The business analysis approach

D.

The stakeholder roles

Buy Now
Question # 71

A business analyst (BA) is working on a set of tasks to establish a governance process for the project. The BA intends to identify who has authority and responsibility to propose changes, who should be involved in the change discussions, and how changes will be documented and communicated. Which of the following are the inputs that would help the BA complete the task?

Options:

A.

Business analysis approach and stakeholder engagement approach

B.

Governance approach and stakeholder engagement approach

C.

Governance approach and business analysis approach

D.

Stakeholder engagement approach and information management approach

Buy Now
Question # 72

A business analyst (BA) is working on a project to provide a temporary solution that will last for two months. The BA is feeling overwhelmed with the work needed to create the huge number of links to provide full traceability from solution requirements to design for this solution. How can the BA justify omitting all possible links?

Options:

A.

Such traceability is at a lower level of abstraction for this project

B.

The value each link is delivering in this situation is not high

C.

Traceability is a low priority as the BA has other work to complete

D.

It is impossible for anyone to confirm if such links are correct

Buy Now
Question # 73

A project aiming at improving an organization's Net Promoter Score is nearing completion. The business analyst (BA) and stakeholders are evaluating ways to measure the performance of the solution. Which technique may be employed?

Options:

A.

Vendor assessment

B.

Market analysis

C.

Focus groups

D.

Business case

Buy Now
Question # 74

A business analyst (BA) is conducting a workshop with the purpose of analyzing a business process. Stakeholders of different business units are in attendance. Each stakeholder is able to explain their unit's contribution to the process, however, there is no end to end process owner who can provide a consolidated view. Which technique should the BA use to compare the stakeholder's inputs against each other in order to check for consistency and omissions?

Options:

A.

Schedule a follow-up workshop to give more time for additional input

B.

Create a use case scenario that describes the process step by step

C.

Develop a process model with swimlanes to highlight the handoff points

D.

Create a logical data model with the information elicited

Buy Now
Question # 75

Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The team is expressing the difficulty of the requirements and how it will be extremely challenging to complete. When Mark asks about a similar project that the team completed, they insist that this is a different type of requirements though Mark believes that it is not. What is the solution development team appearing to do to the requirements?

Options:

A.

Get the requirements removed from the project scope.

B.

Change the prioritization of the requirements based on overstated complexity of the project work.

C.

Change the prioritization of the requirements based on the past project.

D.

Have the business analyst report the difficulty of the project work to the project customer.

Buy Now
Question # 76

There are many stakeholders that need to be involved in the allocated requirements. One of the stakeholders in the task will be responsible for verifying released and solution components. Which stakeholder has this

responsibility?

Options:

A.

Project team

B.

Project manager

C.

Operational support

D.

Tester

Buy Now
Question # 77

As a business analyst, you must identify activities in your business analysis approach. Which one of the following is useful for identifying activities?

Options:

A.

Project management input

B.

BABOK

C.

A list of deliverables

D.

WBS

Buy Now
Question # 78

You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?

Options:

A.

RAM Chart

B.

Affinity Diagram

C.

Stakeholder Analysis

D.

Text-Oriented Chart

Buy Now
Exam Code: CCBA
Exam Name: Certification of Capability in Business Analysis (CCBA)
Last Update: Feb 23, 2025
Questions: 522
CCBA pdf

CCBA PDF

$25.5  $84.99
CCBA Engine

CCBA Testing Engine

$28.5  $94.99
CCBA PDF + Engine

CCBA PDF + Testing Engine

$40.5  $134.99