Question # 109

A certain stakeholder requirement has been analyzed and broken down into several solution requirements, each affecting a different IT system. After solution design, the business analyst (BA) receives feedback that

one of the IT systems will take longer than anticipated to implement. What requirements artifact or technique will assist the BA in better understanding the related requirements?

Options:

A.

MoSCoW prioritization

B.

Backlog management

C.

Requirements documentation

D.

Traceability matrix

Buy Now
Question # 110

A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?

Options:

A.

Stakeholders may refuse the solution.

B.

Requirements metrics may not be measurable.

C.

The BA may significantly impact other aspects of the project timeline.

D.

The business need may change.

Buy Now
Question # 111

A business analyst (BA) identifies a design option that enhances the performance of the business by automating repetitive tasks that require multiple staff touchpoints to complete a single task. Which type of improvement opportunity is identified by the BA?

Options:

A.

Identify additional capabilities

B.

Increase efficiencies

C.

Reduce costs

D.

Improve access to information

Buy Now
Question # 112

An organization is engaged in an effort to streamline the online customer experience. The business analyst (BA) prepares a business analysis information package to discuss the changes the customer will experience. Which one of the following tools will assist the BA in this discussion?

Options:

A.

Context Diagram

B.

Data Dictionary

C.

Visual Prototype

D.

Business Rules

Buy Now
Question # 113

There are competing needs from the different business areas that will use a new system. The business analyst (BA) sets up a weekly meeting with a structured agenda to review the total effort, cost, business impact and risk of each requirement with the business leads to determine what is included in each release of the solution. What approach has the BA defined?

Options:

A.

Prioritization approach

B.

Communication approach

C.

Collaboration approach

D.

Traceability approach

Buy Now
Question # 114

A survey on a new system was conducted after the chief executive officer (CEO), who is also the project sponsor, expressed concerns about the uptake of the new system. The CEO is neither sure that the concerns are valid nor whether the survey was conclusive about the success of the project. The business analyst (BA) has been tasked to address the concerns expressed by the CEO and evaluate the results of the survey. What must the BA do to determine that the system is performing as intended and address the concerns of the CEO?

Options:

A.

Evaluate the new system against competitor applications

B.

Confirm the satisfaction of business requirements

C.

Conduct another survey to validate the original results

D.

Validate performance measures and alignment with KPIs

Buy Now
Question # 115

The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?

Options:

A.

Create a process model

B.

Develop a work breakdown structure

C.

Build an entity-relationship diagram

D.

Construct a decision tree

Buy Now
Question # 116

A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?

Options:

A.

Quality control checklist

B.

Communication plan

C.

Decision analysis

D.

Risk review

Buy Now
Question # 117

The following chart represents attendance of subject matter experts (SME) and the solution owner for a requirements review and approval meeting held weekly by a business analyst (BA).

The requirements package was approved by the solution owner during the May 30 meeting. After implementation of the solution, the BA learns that the users in SME-3 s area are not using the system. Which business analysis activity should the BA have monitored more closely to mitigate this situation?

Options:

A.

Business processes

B.

Requirements scope

C.

Solution performance

D.

Stakeholder engagement

Buy Now
Question # 118

While gathering information during a requirements workshop, a subject matter expert states that it is likely that an organizational restructure will occur in one of the business departments that will be utilizing parts of the new system. As such, the business analyst (BA) should:

Options:

A.

ask the project sponsor to confirm whether and when the restructure will occur.

B.

record a risk that requirements may change and further explore the likelihood and impact of the risk.

C.

note the constraint that the solution must be flexible to accommodate different roles after implementation.

D.

proceed as if the business unit will not be restructured and wait for the organization to confirm otherwise.

Buy Now
Question # 119

A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject

matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase. What should the business analyst (BA) have done to prevent the delay?

Options:

A.

Selected a different project methodology

B.

Requested new SMEs participate in the project

C.

Modified the governance structure

D.

Engaged in consistent collaboration

Buy Now
Question # 120

A project is being initiated to enhance an on-line product because sales have declined for over a year. The company leader’s ant confident that all of the skills needed to improve the product exist within the company. By enhancing the product, sales will increase and new customers will emerge. A business analyst (BA) will help the enhancement project by first:

Options:

A.

documenting the requirements.

B.

identifying the stakeholders.

C.

implementing a suitable solution.

D.

evaluating the business need.

Buy Now
Question # 121

A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?

Options:

A.

Risk-neutral

B.

Risk-optimizing

C.

Risk-averse

D.

Risk-soaking

Buy Now
Question # 122

A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively. What should the BA do to prevent a similar situation in the future?

Options:

A.

Plan business analysis governance

B.

Verify requirements

C.

Perform stakeholder analysis

D.

Validate requirements

Buy Now
Question # 123

A business analyst (BA) is examining the relationships between elicited requirements on a project. What quality criteria must be satisfied when the BA is defining requirements relationships?

Options:

A.

Priority

B.

Complexity

C.

Necessary

D.

Source

Buy Now
Exam Code: CCBA
Exam Name: Certification of Capability in Business Analysis (CCBA)
Last Update: Feb 23, 2025
Questions: 522
CCBA pdf

CCBA PDF

$25.5  $84.99
CCBA Engine

CCBA Testing Engine

$28.5  $94.99
CCBA PDF + Engine

CCBA PDF + Testing Engine

$40.5  $134.99