A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed.
Following are the durations of all tasks:
Task Duration
A) Four weeks
B) Two weeks
C) Six weeks
D) Three weeks
E) Seven weeks
F) One week
G) Two weeks
H) Nine weeks
Which of the following tasks are on the critical path?
A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the
following is the project a part?
Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members.
Which of the following steps should the PM take to make the meetings more productive? (Select two.)
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?