Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-004 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 114

A new project manager is working in an environment where resources report to another supervisor. The

project manager is having difficulty with a particular member and wants to escalate the issue. Which of the

following documents should the project manager consult?

Options:

A.

Issue log

B.

RACI chart

C.

Risk management plan

D.

Organizational chart

Buy Now
Question # 115

The project manager needs to motivate the team; however, is an insufficient budget for awards.

Which of the following motivating agents is the MOST appropriate option the project manager can utilize?

Options:

A.

Reduce the workload

B.

Replace resources

C.

Extend the timeline

D.

Provide additional responsibility

Buy Now
Question # 116

A new project charter is being drafted.

Which of the following would be the BEST source for the high-level project requirements?

Options:

A.

Sponsor

B.

Project manager

C.

Project management office

D.

Project team

Buy Now
Question # 117

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.

Which of the following is the MOST likely reason?

Options:

A.

Established communication plan

B.

Scope creep

C.

Resource constraints

D.

Iterative approach

Buy Now
Question # 118

Which of the following documents need to be updated as events occur during a project? (Select TWO).

Options:

A.

Change request

B.

Risk register

C.

Meeting minutes

D.

Issue log

E.

Status report

Buy Now
Question # 119

A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?

Options:

A.

Project schedule

B.

Issue log

C.

Risk register

D.

Scope statement

Buy Now
Question # 120

Which of the following charts is a mathematical diagram used to values for two variables for a set of data?

Options:

A.

Histogram

B.

Fishbone

C.

Gantt

D.

Scatter

Buy Now
Question # 121

Which of the following primary factors are used to prioritize the development of risk response strategies?

(Choose two.)

Options:

A.

Likelihood

B.

Timeline

C.

Impact

D.

Quality

E.

Cost

Buy Now
Question # 122

Which of the following captures unforeseen activities throughout the project that need attention and resolution?

Options:

A.

Gantt chart

B.

Action items

C.

Project schedule

D.

Meeting minutes

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Feb 23, 2025
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99