Question # 44

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

Options:

A.

Pareto chart

B.

Fishbone diagram

C.

Process diagram

D.

Run chart

Buy Now
Question # 45

A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?

Options:

A.

Vendors

B.

Key stakeholders

C.

Resources

D.

Project team

E.

Business analysts

Buy Now
Question # 46

During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

Options:

A.

Change request

B.

Risk mitigation

C.

Change control

D.

Scope creep

Buy Now
Question # 47

A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?

Options:

A.

Closing

B.

Executing

C.

Planning

D.

Monitoring and controlling

Buy Now
Question # 48

A project sponsor has repeatedly indicated dissatisfaction with the resjits o' several projects being managed by different individuals and consisting of different teams within the organization. Which of the following is the best action for management to take NEXT?

Options:

A.

Change to a matrix organizational structure.

B.

Audit the project management process.

C.

Enforce the use of EVM.

D.

Remove the project sponsor.

Buy Now
Question # 49

Which of the following metrics are used to determine a project's EAC?

Options:

A.

Baseline costs plus actual costs

B.

Forecasted costs plus actual costs

C.

Planned costs minus actual costs

D.

Forecasted costs minus actual costs

Buy Now
Question # 50

Which of the following BEST describes the relationship between portfolios, projects, and programs?

Options:

A.

A group of programs makes up a project, and all of an organization's projects make up a portfolio.

B.

A group of projects makes up a program, and all of an organization's programs make up a portfolio.

C.

A group of portfolios makes up a program, and all of an organization's programs make up a project.

D.

A group of projects makes up a portfolio, and all of an organization's portfolios make up a program.

Buy Now
Question # 51

A manager is reviewing some projects with two project managers who are working on the financial system.

Which of the following BEST describes this type of review?

Options:

A.

Operations

B.

Project

C.

Portfolio

D.

Program

Buy Now
Question # 52

A project’s stakeholders have not been informed of project updates and milestones by the CCB and project

team. The stakeholders have threatened to withdraw project support. Which of the following should the project

manager do to get buy-in from the stakeholders for the project?

Options:

A.

Update the communications plan to include the stakeholders

B.

Expedite completion of the project before support is withdrawn by the stakeholders

C.

Revise the quality management plan to include the project stakeholders

D.

Increase the number of status reports provided to the project stakeholders

Buy Now
Question # 53

When developing a project schedule, which of the following tools would be MOST beneficial?

Options:

A.

Gantt chart

B.

Network diagram

C.

Fishbone chart

D.

Chain diagram

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Feb 22, 2025
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99