Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-004 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 14

A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?

Options:

A.

Trust the contractor to do the job well because the company has been in business for a long time.

B.

Tell the contractor that the company is responsible for any damage done to underground lines.

C.

Immediately fix any broken lines that are hit during construction.

D.

Ensure the contractor has the appropriate utility maps.

Buy Now
Question # 15

Which of the following documents would MOST likely provide a broad, non-customized overview of a product or service?

Options:

A.

SLA

B.

RFI

C.

RFP

D.

SOW

Buy Now
Question # 16

During a project, the project manager realizes some staff positions may be eliminated. Which of the following is the best NEXT step for the project manager to take?

Options:

A.

Communicate the concern with the project sponsor.

B.

Identify replacement resources.

C.

Review and update the project schedule.

D.

Add the risk to the risk register.

Buy Now
Question # 17

A project sponsor wants to know which tasks are next in the project but is unable to find this information.

Which of the following may need to be adjusted?

Options:

A.

Scope document

B.

Status report

C.

Issue log

D.

Risk log

Buy Now
Question # 18

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur.

Which of the following will assist the project team with building the schedule?

Options:

A.

Task sequencing

B.

Task predecessors

C.

Task dependencies

D.

Task prioritizing

Buy Now
Question # 19

Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project.

Which of the following describes the information the new ticketing system would provide?

Options:

A.

RTM

B.

KPIs

C.

BAC

D.

ETC

Buy Now
Question # 20

Which of the following would MOST likely be considered a project?

Options:

A.

Performing scheduled maintenance

B.

Picking and shipping a warehouse order

C.

Troubleshooting a company-wide network issue

D.

Remodeling a house

Buy Now
Question # 21

A Chief Executive Officer (CEO) has approached a project team member to request a project change.

Which of the following would be the BEST step for the project manager to take to prevent scope creep?

Options:

A.

Deny the CEO’s request.

B.

Implement the project change.

C.

Submit the request to the CCB.

D.

Ask the CEO to follow the communications plan.

Buy Now
Question # 22

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

Options:

A.

Risk identification

B.

Gate review

C.

Resource allocation

D.

Resource leveling

Buy Now
Question # 23

Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.

Which of the following steps should the project manager take NEXT?

Options:

A.

Supply Ann with the requested tablet.

B.

Have Ann submit a change request.

C.

Provide Ann with a copy of the project management plan.

D.

Inform Ann that she will receive what has been authorized.

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Feb 22, 2025
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99