Which of the following describes some of the features of the Agile methodology?
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are NOST likely missing from the project? (Select two.)
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a
duration of one day. Which of the following represents the critical path?
A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark a significant change in approach from previous projects. Which of the following should the project manager contact for guidance and approval for the new methodology?
An influential stakeholder has left the organization. Which of the following documents MOST likely needs to be updated?
A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?