Question # 54

Which of the following describes some of the features of the Agile methodology?

Options:

A.

It uses a direct approach, Gantt charts, and a ticketing system.

B.

It uses an indirect approach, spreadsheets for documentation, and change request documents.

C.

It uses an iterative approach, backlogs, and burndown charts.

D.

It uses a step-by approach, an issue log, and pie charts.

Buy Now
Question # 55

Which of the following should be included in an effective SOW?

Options:

A.

Lessons learned

B.

Procurement process

C.

Corrective action plan

D.

Project objectives

Buy Now
Question # 56

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.

Which of the following are NOST likely missing from the project? (Select two.)

Options:

A.

Project charter

B.

Organizational chart

C.

Scope document

D.

Status report

E.

Business case

F.

Project plan

Buy Now
Question # 57

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.

Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a

duration of one day. Which of the following represents the critical path?

Options:

A.

Five days

B.

Six days

C.

Seven days

D.

Eight days

Buy Now
Question # 58

A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

Options:

A.

Assign a different team member to resolve the issue before the next status meeting.

B.

Review the issue with the assigned team member to determine a due date.

C.

Set a due date to resolve the issue and inform the assigned team member.

D.

Report the team member to a functional manager for disciplinary action.

Buy Now
Question # 59

The executive sponsor asks a project manager to summarize the following for a project:

1. Final capital expenditures.

2. Anticipated cost of new employee resources to support the solution.

3. Maintenance estimates.

Which of the following information should the project manager provide?

Options:

A.

Cost baseline

B.

Burn rate

C.

Cost variance report

D.

Total project cost

Buy Now
Question # 60

A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark a significant change in approach from previous projects. Which of the following should the project manager contact for guidance and approval for the new methodology?

Options:

A.

Project coordinator

B.

Project team

C.

Project management office

D.

Project sponsor

Buy Now
Question # 61

An influential stakeholder has left the organization. Which of the following documents MOST likely needs to be updated?

Options:

A.

Incident response plan

B.

Issue log

C.

Communication plan

D.

Project plan

Buy Now
Question # 62

A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?

Options:

A.

Present the change request to the CAB.

B.

Evaluate the change with the project team.

C.

Set up a face-to-face meeting with the project sponsor

D.

Organize a steering committee meeting.

Buy Now
Question # 63

Agate review also is considered:

Options:

A.

a method to make changes to resources.

B.

an update to an incident response plan

C.

a checkpoint to review schedule changes

D.

a type of audit occurring during the project.

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Feb 22, 2025
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99