Question # 24

A project has been created, and the project team has been identified. Which of the following is the NEXT step?

Options:

A.

Release an article on the company blog.

B.

Conduct a company town hall.

C.

Host a kickoff meeting.

D.

Post a notice on social media.

Buy Now
Question # 25

A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project.

Which of the following has MOST likely occurred?

Options:

A.

Scope creep

B.

Gold plating

C.

Task reprioritization

D.

Lack of requirements

Buy Now
Question # 26

Which of the following is an example of quantitative risk management?

Options:

A.

Prioritizing risk mitigation response procedures

B.

Determining annual loss expectancy

C.

Sorting risks into three categories

D.

Assigning an owner to each identified risk

Buy Now
Question # 27

A project manager wants to determine the percentage of a project's budgeted costs versus expenditures.

Which of the following calculations should the project manager perform?

Options:

A.

Burn rate

B.

Critical path analysis

C.

EV

D.

EAC

Buy Now
Question # 28

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.

Which of the following schedule compression techniques should be used by the project manager?

Options:

A.

Rescheduling

B.

Crashing

C.

Rebaselining

D.

Control scope

Buy Now
Question # 29

Which of the following normally would be completed prior to a vendor responding to an RFP?

Options:

A.

PO

B.

Contract

C.

SLA

D.

NDA

Buy Now
Question # 30

Which of the following describes how a project is related to a program?

Options:

A.

A program is a combination of multiple projects.

B.

A program contains an element of the project.

C.

A program is a part of a project.

D.

A program uses half of the project’s budget.

Buy Now
Question # 31

A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users.

In which of the following components of the project plan should this be documented?

Options:

A.

Scope statement

B.

Issues log

C.

WBS

D.

Change form

Buy Now
Question # 32

A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.

Which of the following strategies is the project manager applying?

Options:

A.

Accepting

B.

Mitigating

C.

Avoiding

D.

Transferring

Buy Now
Question # 33

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Options:

A.

EAC

B.

BAC

C.

TCPI

D.

ETC

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Feb 22, 2025
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99