Halloween Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PDF CCP Study Guide

Page: 12 / 13
Question 48

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

Options:

A.

Ratio/level of effort

B.

Start/finish

C.

Units completed

D.

Incremental milestone

Question 49

The discount rate is a measure used to convert cash flow streams occurring to different points in time to a common base called the net present worth. What is the discount rate based upon?

Options:

A.

Inflation and interest rates

B.

The interest rate which the client will have to pay on his loan

C.

Bank rate

D.

The rate of inflation

Question 50

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

Options:

A.

$31,875

B.

$12,550

C.

$29,600

D.

$13,515

Question 51

Which of the following best describes the three key participants for projects that are executed under a three-party contractual relationship?

Options:

A.

Contracting officer, contractor, and contractor project manager

B.

Procurement officer, underwriter, and project manager

C.

Owner, engineer, contractor

D.

Client, project manager, procurement manager

Page: 12 / 13
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Oct 21, 2024
Questions: 189
CCP pdf

CCP PDF

$24  $80
CCP Engine

CCP Testing Engine

$28.5  $95
CCP PDF + Engine

CCP PDF + Testing Engine

$39  $130