Question 20

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

Options:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Question 21

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

Options:

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Question 22

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the range of estimated quantities?

Options:

A.

$26.78 to $75.00

B.

$485

C.

$45 to $530

D.

$48.22

Question 23

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

What is the range of unit costs?

Options:

A.

$21.57

B.

$26.65

C.

$48.22

D.

$485.00

Page: 5 / 13
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Nov 21, 2024
Questions: 189
CCP pdf

CCP PDF

$28  $80
CCP Engine

CCP Testing Engine

$33.25  $95
CCP PDF + Engine

CCP PDF + Testing Engine

$45.5  $130