Question 44

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%

B.

75%

C.

90%

D.

84%

Question 45

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?

Options:

A.

Productivity efficiency factor

B.

Value engineering

C.

Cash flow

D.

The learning curve

Question 46

Which of the following are used for profitability analysis in a construction company?

Options:

A.

Sum of years digits

B.

Return on Investment (ROI) and Rate of Return (ROR)

C.

Opportunity costs

D.

Booked costs

Question 47

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

Options:

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Page: 11 / 13
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Oct 21, 2024
Questions: 189
CCP pdf

CCP PDF

$24  $80
CCP Engine

CCP Testing Engine

$28.5  $95
CCP PDF + Engine

CCP PDF + Testing Engine

$39  $130