Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

CCP Reviews Questions

Page: 9 / 13
Question 36

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following would NOT be considered part of a project cost and schedule forecast?

Options:

A.

Usage of contingency

B.

Current trends of time and money

C.

Peripherals report

D.

Changes to the project execution plan

Question 37

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?

Options:

A.

Continuous compounding rate

B.

Simple interest rate

C.

Minimum attractive rate of return

D.

Nominal interest rate

Question 38

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

Options:

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Question 39

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

Options:

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Page: 9 / 13
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Nov 21, 2024
Questions: 189
CCP pdf

CCP PDF

$28  $80
CCP Engine

CCP Testing Engine

$33.25  $95
CCP PDF + Engine

CCP PDF + Testing Engine

$45.5  $130