Question 88

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Question 89

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Question 90

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

Options:

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Question 91

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Page: 22 / 26
Exam Code: APM-001
Exam Name: Associate in Project Management (APM)
Last Update: Dec 24, 2024
Questions: 0
APM-001 pdf

APM-001 PDF

$25.5  $84.99
APM-001 Engine

APM-001 Testing Engine

$28.5  $94.99
APM-001 PDF + Engine

APM-001 PDF + Testing Engine

$255  $850