APM-001 Exam Results

Page: 16 / 26
Question 64

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Options:

A.

$800

B.

$1000

C.

$1250

D.

$1800

Question 65

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question 66

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question 67

Exhibit A is an example of which of the following types of Sequence Activities?

Options:

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Page: 16 / 26
Exam Code: APM-001
Exam Name: Associate in Project Management (APM)
Last Update: Dec 24, 2024
Questions: 0
APM-001 pdf

APM-001 PDF

$25.5  $84.99
APM-001 Engine

APM-001 Testing Engine

$28.5  $94.99
APM-001 PDF + Engine

APM-001 PDF + Testing Engine

$255  $850