Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Selected APM-001 GAQM: Project Management Questions Answers

Page: 8 / 26
Question 32

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Options:

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Question 33

Which is a communication method used in the Report Performance process?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Question 34

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Question 35

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Page: 8 / 26
Exam Code: APM-001
Exam Name: Associate in Project Management (APM)
Last Update: Nov 7, 2024
Questions: 0
APM-001 pdf

APM-001 PDF

$28  $80
APM-001 Engine

APM-001 Testing Engine

$33.25  $95
APM-001 PDF + Engine

APM-001 PDF + Testing Engine

$297.5  $850