Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

APM-001 Questions Bank

Page: 25 / 26
Question 100

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Question 101

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Question 102

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Question 103

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Page: 25 / 26
Exam Code: APM-001
Exam Name: Associate in Project Management (APM)
Last Update: Nov 7, 2024
Questions: 0
APM-001 pdf

APM-001 PDF

$28  $80
APM-001 Engine

APM-001 Testing Engine

$33.25  $95
APM-001 PDF + Engine

APM-001 PDF + Testing Engine

$297.5  $850