A business analyst (BA) is working on a stakeholder collaboration plan. The main goal is to select the approaches that work best to meet the needs of external and internal stakeholders.
Which aspects should be taken into account?
A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group.
In which of the following can the BA find this information?
In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on the amount of work that the project team is capable of delivering in a given period of time.
Which of the following techniques is the BA recommending?
A business analyst (BA) has been coordinating several meetings with stakeholders to reach consensus regarding the solution design to implement a global currency exchange system for an international bank. Consensus has not been reached yet, although BA has great communication skills and is trusted by all stakeholders. The stakeholders formally approved the business need initially.
Why is there disagreement?
A big construction company has grown into a group of 17 companies spread across the country. The rationale behind forming the group was to become more competitive in bidding for federal and regional government contracts. Another reason was to increase consolidated profitability by lowering the cost of materials and using combined assets more efficiently. Disjointed technological capabilities of the individual companies impede gathering the data needed to make decisions on both handling materials and allocating the resources.
What improvement opportunity does this represent?
While validating requirements for a software implementation project, the business analyst (BA) needs to identify scenarios that would alter the benefit delivered by a requirement.
Which of the following techniques should the BA use to identify such scenarios?
The business analyst (BA) is facilitating a requirements workshop with a large group of diverse stakeholders, some of whom are not entirely familiar with the goals and objectives of the project.
The BA must understand the business domain, corporate culture, group dynamics, and expected outputs to adequately communicate the:
Which of the following represents the duration of activities against a calendar?
Which of the following are directed conversations for gathering ideas, opinions about a product, service, problem, or opportunity?
A company that specialized in manufacturing vending machines for books has been in business for 10 years. As the e-book and online retailing grow, the company perceived that a change is required to respond to the new emerging market forces. However, the change should focus on reusability as much as possible to reduce expenses. After analyzing the current state with the business subject matter experts, the business analyst
(BA) proposed investing in a new business line of vending machines that sell pay per use mobile device phone fast charging stations.
Due to the urgency of this change, the BA was asked to finalize requirements elicitation in the shortest possible time.
Customers who want to utilize the pay per use mobile device fast charging stations may choose one of two features: fully charged (F1) or partially charged (F2). If partially charged is selected, the customer needs to specify their charging needs.
What is the relationship between F1 and F2?