Scenario C: Dependencies and Product Backlog items
During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams
identify many dependencies. This makes it hard for them to choose the work they could pull
into their individual teams for the next Sprint. No matter how they reorganize the Product
Backlog items, they continually find more or new dependencies.
What techniques could help this Nexus manage their dependencies effectively?
(choose the best two answers)
True or False: Scrum Teams must report back to the Nexus Integration Team right after their individual Daily Scrums.