An application has 3 ILFs and 3 EIFs all of average complexity. An enhancement to the system introduces a new screen that references all of the existing ILFs and EIFs, and maintains 1 of the existing ILFs. The enhancement project function point count will take into account:
In an enhancement project an EI is counted as changed because an additional attribute is sent across the boundary. Before the enhancement the EI referenced 2 FTRs and 15 attributes crossed the boundary. How many FPs are measured for the enhancement project?
Four different country managers require a report about the sales turnover for their respective countries. Country managers 1 and 2 require the data to be sorted in the ascending order of the sales, whereas country mangers 3 and 4 require the data to be sorted in the ascending order of sales and profit. How many elementary processes would be counted for the sales turnover report?
A screen that adds an order record to the Order file is being enhanced to capture 10 additional attributes. These new attributes do not fit onto the existing screen, so a new screen is being created to collect the 10 new attributes before creating the Order record. How is the screen counted for the enhancement project?
The user requirements call for a model stock portfolio list to be created. The user will be able to enter selection criteria for the equities to be included in the model stock portfolio list. There is another requirement for the user to be able to save the selection criteria. How many elementary processes would be counted?
An application provides the users with screen help, field sensitive help, and system help. The help information is maintained within another application. How many EQs are counted?
Which category (ies) of data entities is (are) usually identified to satisfy the Functional User Requirements?