Questions 4

X Company is a car manufacturer with significant competition in the market. One of its customers is a large multinational car hire company. Place the correct level of power against the Power of Buyers.

Options:

Buy Now
Questions 5

 

Examine the network diagram shown and identify ALL of the statements below that are true.

Options:

A.

Task C is a predecessor of E

B.

Task G may begin when either Task B or Task F have finished

C.

When Task A is complete, three tasks may begin

D.

Task D is a successor to F

Buy Now
Questions 6

AW is a newly appointed manager of the accounts department in organisation S.  Her appointment has been well received by members of the department who recognise AW as a skilled and well qualified accountant.

 

However, AW has been frustrated by progress in departmental team meetings which tend to be unruly, unproductive and disorganised.  AW recognises a need to improve the effectiveness of the meetings.

 

Which THREE actions should AW take in order to have more effective meetings?

Options:

A.

Produce an agenda at the meeting

B.

Determine the purpose of the meeting

C.

Publish lengthy and detailed minutes

D.

Manage the plan of action

E.

Establish who should attend

F.

Allow attendees to talk through issues with each other independent of the chairperson

Buy Now
Questions 7

Bob is the Finance Director of a manufacturing business selling luggage sucn as suitcases. He decides to undertake a business process re-engineering of the credit control function in order to achieve dramatic

improvements.

What wouldn't be classed as the main improvements bob expects to deliver?

Select ALL that apply.

Options:

A.

To change the culture of the team

B.

To improve security of information

C.

To automate the credit control process to reduce costs

D.

To improve the speed of the process to improve efficiency

E.

To reduce errors in credit control and produce more accurate information

F.

To do this in line with new sophisticated information systems

G.

To improve the motivation of the team

Buy Now
Page: 1 / 15
Exam Code: E2
Exam Name: Project and Relationship Management
Last Update: Nov 21, 2024
Questions: 210
E2 pdf

E2 PDF

$69.65  $199
E2 Engine

E2 Testing Engine

$78.75  $225
E2 PDF + Engine

E2 PDF + Testing Engine

$87.15  $249