Question 68

What is the standard deviation for the estimates in the above problem?

Options:

A.

2

B.

0.5

C.

1.5

D.

0.6

Question 69

Which of the following is an example of contract administration?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Question 70

When does risk monitoring and control occur?

Options:

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Question 71

The purpose of configuration management is to:

Options:

A.

control change during the production only

B.

control change throughout the project

C.

inform the project manager of changes

D.

generate engineering change proposals

E.

insure drawings are updated

Page: 17 / 23
Exam Code: ISEB-PM1
Exam Name: BCS Foundation Certificate in IS Project Management
Last Update: Dec 23, 2024
Questions: 625
ISEB-PM1 pdf

ISEB-PM1 PDF

$25.5  $84.99
ISEB-PM1 Engine

ISEB-PM1 Testing Engine

$28.5  $94.99
ISEB-PM1 PDF + Engine

ISEB-PM1 PDF + Testing Engine

$40.5  $134.99