As the project manager, you are preparing your methods for quality management. You are looking for a method that can demonstrate the relationship between events and their resulting effects. You want to use a method to depict the events that cause a negative effect on quality.
Which of the following is the BEST choice for accomplishing your objective?
A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate.
Who has the PRIMARY responsibility to solve this problem?
A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar time.
What is the FIRST thing you should do?
While reviewing project performance, the project manager determines that the schedule variance is -500.
What is the BEST thing to do?