Question 80

Management wants to be sure that the project is following defined quality standards.

Which of the following should they look at?

Options:

A.

Risk management plan

B.

WBS

C.

Statement of work

D.

Quality audit

Question 81

Which stakeholder is responsible for managing related projects in a coordinated way?

Options:

A.

Sponsor

B.

Portfolio manager

C.

Program manager

D.

Project manager

Question 82

Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?

Options:

A.

Stakeholder management

B.

Monitoring and controlling

C.

Project governance

D.

Project management methodology

Question 83

Which of the following tools or techniques is used for Estimate Activity Duration?

Options:

A.

Critical path

B.

Rolling Wave

C.

PDM

D.

Parametric

Page: 20 / 23
Exam Code: ISEB-PM1
Exam Name: BCS Foundation Certificate in IS Project Management
Last Update: Dec 23, 2024
Questions: 625
ISEB-PM1 pdf

ISEB-PM1 PDF

$25.5  $84.99
ISEB-PM1 Engine

ISEB-PM1 Testing Engine

$28.5  $94.99
ISEB-PM1 PDF + Engine

ISEB-PM1 PDF + Testing Engine

$40.5  $134.99