PRINCE2 Certification Prince2-Practitioner Updated Exam

Page: 8 / 10
Question 32

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?

Options:

A.

Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.

B.

A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.

C.

A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.

Question 33

Scenario:

Techniques, processes and procedures

1. Any threat that may result in a loss of MFH data must be escalated immediately.

Joint agreements

2. Work is to start at the beginning of week 2 (Stage 4).

3. The project will take two years to complete, at an estimated cost of £2.5m.

Tolerances

4. None.

Constraints

5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.

6. Installation work must take place during MFH normal working hours.

7. +£10,000 / -£25,000.

Reporting arrangements

8. Highlight Report every Monday by 10.00 am.

9. The report must contain a summary of all products worked on during the previous week.

10. Project Manager must be notified of any issues immediately by telephone.

Problem handling and escalation

11. Impact analysis of all issues must be completed within 24 hours.

Extracts or references

12. The Stage Plan for stage 4 is available from Project Support.

Approval method

13. Project Assurance will review the completed Work Package and confirm completion

Which 2 statements apply to either the Extracts or references or Approval method sections?

Options:

A.

Delete entry 12 because this should be the Team Plan not the Stage Plan.

B.

A suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'.

C.

Move entry 13 to Reporting arrangements because this describes how completion will be advised to the

D.

Project Manager.

E.

Delete entry 13 because this is NOT a Project Assurance responsibility.

F.

Add 'The Project Manager is to be advised of completion of the Work Package by email'.

Question 34

Which of the following is not a factor to consider when determining the length of a stage?

Options:

A.

The amount of resources available h the short term

B.

How far ahead you can sensibly plan n detail

C.

The technical stages within the project

D.

The amount of risk associated with the project

Question 35

Who is responsible for confirming stage and project progress against agreed tolerances?

Options:

A.

Project Support

B.

Executive

C.

Project Assurance

D.

Project Manager

Page: 8 / 10
Exam Name: PRINCE2 Practitioner Exam
Last Update: Nov 17, 2024
Questions: 282
Prince2-Practitioner pdf

Prince2-Practitioner PDF

$24  $80
Prince2-Practitioner Engine

Prince2-Practitioner Testing Engine

$28.5  $95
Prince2-Practitioner PDF + Engine

Prince2-Practitioner PDF + Testing Engine

$39  $130