Question 20

MANAGING A STAGE BOUNDARY

The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.

Which action should the project manager undertake as part of the 'update the business case' activity?

Options:

A.

Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.

B.

Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.

C.

Review the performance of the external suppliers who worked on delivery of the 'e-learning course' during stage 3.

D.

Re-plan when the number of learners using the pilot course, and their increased knowledge, will be measured during stage 4.

Question 21

Scenario

Additional Information

Product Description

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Which is a correctly defined acceptance criterion for the running cost of the outsourced service?

Options:

A.

Must be kept to a minimum.

B.

Must be kept to a level acceptable to the Ministry of Food Hygiene.

C.

Subject to market conditions.

D.

The annual increase to be less than half the rate of inflation.

Question 22

Scenario

Additional Information

Product Description

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Which is a correctly defined acceptance criterion for the transferred staff?

Options:

A.

No staff are to be left behind.

B.

Staff should be transferred as soon as possible.

C.

All legal requirements are adhered to for the transfer of staff.

D.

Retained staff should be of reasonable competence to maintain the SLA.

Question 23

Which of the following statements are True:

1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.

2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.

3. Quality control focuses on the operational techniques and activities used to carry out quality inspections

4. Quality assurance ensures that quality methods are being correctly followed.

Options:

A.

1, 2 & 3

B.

1, 3 & 4

C.

1, 2 & 4

D.

2, 3 & 4

Page: 5 / 10
Exam Name: PRINCE2 Practitioner Exam
Last Update: Nov 17, 2024
Questions: 282
Prince2-Practitioner pdf

Prince2-Practitioner PDF

$24  $80
Prince2-Practitioner Engine

Prince2-Practitioner Testing Engine

$28.5  $95
Prince2-Practitioner PDF + Engine

Prince2-Practitioner PDF + Testing Engine

$39  $130