Question 36

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

  • Design for each month - correctly showing at public holidays and new company logo
  • Selected photographs- 12 professionally-produced photographs, showing different members of staff
  • Selected paper and selected envelope - for printing and mailing the calendar
  • Chosen label design - a competition to design a label will be held as part of this project
  • List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

  • Create the customer fast using information from the Accounts and Marketing departments
  • Confirm compliance with the Data Protection Legislation
  • Create a design for each month - this will be done by the internal creative team
  • Select and appoint a professional photographer
  • Gather photograph design ideas from previous project and agree photographic session schedule
  • Prepare a production cost forecast
  • Select paper and envelope.

Stage 3 will include the activities to:

  • Produce and select tie professionally-taken photographs
  • Hold the label design competition and choose the label design
  • Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?

Options:

A.

There can be no time tolerances for any of the stages.

B.

All of the project level time tolerance can be allocated to stage 2.

C.

The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.

D.

Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.

Question 37

During stage 1 the level of performance expected from the service provider was changed.

After this change was agreed which of these products will require updating?

Options:

A.

Project Brief because this is maintained throughout the project to reflect the customer's quality expectations.

B.

Project Product Description because this contains details of the expected performance of the project's products.

C.

Quality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented.

Question 38

While deciding on how the work of the project should be approached the following were considered.

Which statement is appropriate for inclusion in the project approach heading in the Project Brief?

Options:

A.

The Project Manager will involve the selected service provider in the creation of the Stage Plan for stage 4.

B.

New up-to-date software will be obtained to produce the graphical sections of the Project and Stage Plans.

C.

The detailed designs (future process, systems, operating and organization models) will be based on the existing high-level designs.

Question 39

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

Which statement applies to the Stakeholder analysis: Interested parties section?

Options:

A.

Add 'Internal Creative Team'.

B.

Delete entry 11 because the photographer is internal to the project management team.

C.

Delete entry 12 because the printing of the calendars is outside of the scope

Page: 9 / 10
Exam Name: PRINCE2 Practitioner Exam
Last Update: Nov 17, 2024
Questions: 282
Prince2-Practitioner pdf

Prince2-Practitioner PDF

$24  $80
Prince2-Practitioner Engine

Prince2-Practitioner Testing Engine

$28.5  $95
Prince2-Practitioner PDF + Engine

Prince2-Practitioner PDF + Testing Engine

$39  $130