Question # 44

In which project delivery method does the owner typically engage a contractor to both design and construct the facility under a single agreement, facilitating faster project completion?

Options:

A.

Design-Bid-Build

B.

Design-Build

C.

Construction Manager at Risk

D.

Engineering Procurement Construction Management

Buy Now
Question # 45

A performance audit is focused on evaluating the

Options:

A.

organization's adherence to ethical standards

B.

compliance with environmental regulations

C.

accuracy of financial reporting

D.

effectiveness of operations for outcomes

Buy Now
Question # 46

What role does timing play in a quality audit plan?

Options:

A.

It aligns with project milestones and deliverables

B.

It ensures effective monitoring at appropriate intervals

C.

It schedules when to update project software

D.

It plans the annual general meeting dates

Buy Now
Question # 47

Which of the following statements accurately describes the connection between a strengths-weaknesses-opportunities-threats (SWOT) analysis and a construction project's strategic risk management?

Options:

A.

The effectiveness of a SWOT analysis depends on how many strengths and opportunities are identified.

B.

A SWOT analysis should focus predominantly on external threats to manage risk effectively.

C.

The use of a SWOT analysis is primarily judged by how quickly it can be conducted.

D.

A SWOT analysis addresses internal and external factors and provides a balance of positive and negative elements.

Buy Now
Question # 48

What is the primary benefit of involving local small businesses and suppliers in project contracting?

Options:

A.

It supports the local economy and leverages regional experience

B.

It centralizes project management tasks

C.

It limits the scope of project audits and communication with external entities

D.

It automates project reporting functions

Buy Now
Question # 49

Which of the following approaches best allows a project manager to determine key stakeholders involved in the design process for each discipline?

Options:

A.

Analyzing the project scope and identifying which disciplines have significant impacts on project outcomes

B.

Limiting stakeholder involvement to those with financial investments in the project

C.

Involving senior management from each discipline as key stakeholders

D.

Choosing stakeholders based on their availability rather than their impact on the design process

Buy Now
Question # 50

What is the primary purpose of design verification in the construction project management process?

Options:

A.

Confirm that design outputs fulfill the design inputs

B.

Check if the final construction matches the initial design ideas using visual assessments

C.

Determine the cost-effectiveness of the design outputs

D.

Evaluate the performance of the construction team

Buy Now
Question # 51

What is the most important element of reviewing an operations and maintenance manual to ensure it meets the intent of the final turnover documentation?

Options:

A.

The manuals include contact information for all project contractors.

B.

The manuals are approved by the project management team.

C.

The manuals provide detailed operational procedures for installed systems.

D.

The manuals are available in multiple languages and include a glossary of terms.

Buy Now
Question # 52

Which of the following negative outcomes is most likely to occur when quality resources are demobilized prematurely at the end of a construction project?

Options:

A.

Increased need for interim management

B.

Immediate reduction in operational costs

C.

Potential delay in project deliverables

D.

Increased risk of non-conformance issues

Buy Now
Exam Code: CCQM
Exam Name: Certified Construction Quality Manager
Last Update: Apr 2, 2025