Question # 14

Within a quality management plan, quality audits are defined as

Options:

A.

an optional activity based on available resources

B.

a method to assess the financial aspects of the project

C.

a systematic process to verify compliance with quality standards

D.

a single review at the end of a project

Buy Now
Question # 15

Well-defined criteria contribute to the procurement process by

Options:

A.

providing a benchmark for evaluating vendor proposals and quality

B.

simplifying the design phase by pre-defining all elements

C.

ensuring faster delivery times from suppliers

D.

eliminating the need for contract negotiations with suppliers

Buy Now
Question # 16

What is the most effective way to ensure that nonconforming work on a punch list is properly closed?

Options:

A.

Reassess each punch list item to verify compliance with contract specifications before closure.

B.

Delay closure until all project phases are complete.

C.

Close items based on the subcontractor's assurances.

D.

Close nonconforming items as they are reported by any project team member.

Buy Now
Question # 17

Which of the following attributes of measurement systems is primarily evaluated during a measurement systems analysis?

Options:

A.

Cost-effectiveness

B.

Precision

C.

Aesthetic design

D.

Supplier diversity

Buy Now
Question # 18

Which of the following should be the first priority when preparing quality objectives for operations and maintenance (O&M) to sustain quality based on customer expectations?

Options:

A.

Balancing budget constraints with customer-driven quality objectives

B.

Defining objectives that align with customer needs and expectations

C.

Optimizing internal efficiency while considering customer requirements

D.

Setting objectives that reflect long-term business goals in addition to maintenance programs

Buy Now
Question # 19

A CCQM is managing a construction project, and their team has recently experienced issues with a long-time supplier who provides critical building materials. Over the past three months, the supplier has delivered late on multiple occasions and there has been a notable increase in material defects. However, the supplier has historically offered the lowest price and has been awarded additional contracts based on this. Which of the following approaches should the CCQM take to address the issue?

Options:

A.

Evaluate the supplier's recent performance using quality and delivery KPIs, and consider withholding future contracts until improvements are demonstrated.

B.

Focus on the historical low cost provided by the supplier and continue awarding more contracts based on pricing.

C.

Rely on subjective feedback from team members who have worked with the supplier in the past and have positive relationships with them.

D.

Conduct a one-time evaluation based on the most recent delivery issues, and search for a replacement supplier.

Buy Now
Question # 20

What is the most important factor to consider when establishing criteria for final inspection, testing, and commissioning in a construction project?

Options:

A.

Scheduling the final inspection at the earliest convenience

B.

Ensuring the presence of all project stakeholders during the final inspection

C.

Determining the total number of personnel required to conduct the final inspections

D.

Confirming that all systems operate according to design specifications

Buy Now
Question # 21

How should a quality manager address conflicting feedback from different disciplines during the design process?

Options:

A.

By choosing the feedback from the most technically advanced discipline

B.

By avoiding conflicting feedback to prevent delays in the design process

C.

By considering feedback from the highest authority in the project hierarchy

D.

By facilitating a consensus-building session to align feedback with project quality objectives

Buy Now
Question # 22

When evaluating an improvement methodology, which of the following methods is best for assessing integration of Cost of Quality (CoQ) with Lean principles?

Options:

A.

Evaluating if lean initiatives align with identified CoQ areas, reducing waste and non-value-added activities

B.

Assume that lean practices automatically reduce CoQ without further analysis

C.

Focus on the fastest lean tools regardless of their impact on CoQ

D.

Implement lean tools in isolation from CoQ considerations to simplify the process

Buy Now
Question # 23

What benefit does integrating stakeholder feedback into the quality management plan provide?

Options:

A.

Eliminates any project conflicts

B.

Reduces overall project cost

C.

Speeds up the project timeline

D.

Enhances buy-in

Buy Now
Exam Code: CCQM
Exam Name: Certified Construction Quality Manager
Last Update: Apr 2, 2025
Questions: 165
CCQM pdf

CCQM PDF

$25.5  $84.99
CCQM Engine

CCQM Testing Engine

$28.5  $94.99
CCQM PDF + Engine

CCQM PDF + Testing Engine

$40.5  $134.99