New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PSP Exam Dumps - AACE International Professional Level Questions and Answers

Page: 1 / 11
Questions 4

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

Options:

A.

C.

B.

B.

C.

S.

D.

W.

Buy Now
Questions 5

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Buy Now
Questions 6

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Buy Now
Questions 7

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Options:

A.

02-19-04

B.

03-21-04

C.

03-11-04

D.

03-20-04

Buy Now
Page: 1 / 11
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jan 11, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99