Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PSP Exam Dumps - AACE International Professional Level Questions and Answers

Question # 34

What is the remaining work duration of Active D?

Options:

A.

4.

B.

11

C.

8.

D.

3.

Buy Now
Question # 35

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.9% (1 : 25.708)

B.

2.3% (1 : 43.501).

C.

9.1% (1 : 11.000).

D.

8.6% (1 : 11.591)

Buy Now
Question # 36

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

Options:

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Buy Now
Question # 37

Identify the late finish to develop plans and specs.

Options:

A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Buy Now
Question # 38

If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

Options:

A.

12.

B.

14.

C.

13.

D.

Cannot be determined.

Buy Now
Question # 39

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Buy Now
Question # 40

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Buy Now
Question # 41

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

Options:

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Buy Now
Question # 42

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Options:

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

Buy Now
Question # 43

All the following describe the critical path of a schedule EXCEPT:

Options:

A.

Determined by network logic and is the chain of activities that controls the overall project completion time.

B.

Frequently defined as the shortest path through the schedule.

C.

Changed by redefining the network logic or changing activity durations or both.

D.

The series of activities having the least amount of total float.

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Feb 22, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99