Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PSM-I Exam Dumps - Scrum Professional Scrum Master Questions and Answers

Question # 54

Which topics should be discussed in the Sprint Review? (Choose the best answer.)

Options:

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

The product Increment.

D.

All of the above.

Buy Now
Question # 55

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

Options:

A.

A proportional amount of time on analysis, design, programming, testing, and documentation.

B.

As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.

C.

All development work and at least some testing.

D.

As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”.

Buy Now
Question # 56

You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)

Options:

A.

The desire to maintain a stable velocity.

B.

The benefit of Development Teams figuring out a solution for themselves.

C.

The need to have enough work to keep all Development Team members busy.

D.

The ability of the Development Teams to produce integrated Increments.

Buy Now
Question # 57

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

Options:

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Buy Now
Question # 58

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

Options:

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

Buy Now
Question # 59

Which of the following are roles on a Scrum Team? (Choose all that apply.)

Options:

A.

Users

B.

Scrum Master

C.

Product Owner

D.

Development Team

E.

Customers

Buy Now
Question # 60

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

Options:

A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Buy Now
Question # 61

When a Development Team is having trouble delivering a working Increment because they don’t understand a functional requirement, what should they do?

Options:

A.

Add a specialist to the Development Team.

B.

Partially complete the functionality, and discuss the remaining work at the Sprint Review.

C.

Collaborate with the Product Owner to determine what is possible and acceptable.

D.

Defer the work to a more appropriate Sprint.

Buy Now
Question # 62

When is it most appropriate for a Development Team to change the definition of “Done”?

Options:

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Buy Now
Question # 63

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Buy Now
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Feb 2, 2025
Questions: 250
PSM-I pdf

PSM-I PDF

$29.75  $84.99
PSM-I Engine

PSM-I Testing Engine

$33.25  $94.99
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$47.25  $134.99