Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PSM-I Exam Dumps - Scrum Professional Scrum Master Questions and Answers

Question # 24

Which approach is best for Scrum Teams in order to produce valuable Increments? (Choose the best answer.)

Options:

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team is accountable for developing functionality from beginning to end.

C.

Each Scrum Team works on an independent set of components.

D.

Each Scrum Member works only as an independent layer of the system.

Buy Now
Question # 25

What is the recommended size for a Development Team?

Options:

A.

7 plus or minus 3.

B.

At least 7.

C.

9.

D.

3 to 9.

Buy Now
Question # 26

Who owns the Sprint Backlog?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

Buy Now
Question # 27

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Buy Now
Question # 28

When must the Product Owner participate in the Dairy Scrum? (choose the best answer)

Options:

A.

When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer

B.

When the Product Owner needs to represent the stakeholders point of view to the Developers

C.

When there are impediments to discuss

D.

When the Scrum Master asks the Product Owner to attend

Buy Now
Question # 29

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

Options:

A.

Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B.

Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C.

Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D.

Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

E.

Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.

Buy Now
Question # 30

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

Options:

A.

By ensuring the meetings start and end at the proper time.

B.

By removing impediments that hinder the Development Team.

C.

By facilitating Development Team decisions.

D.

By keeping high value features high in the Product Backlog.

Buy Now
Question # 31

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

Options:

A.

Reorder the Product Backlog.

B.

Pull Product Backlog items for the Sprint.

C.

Do the work planned in the Sprint Backlog.

D.

Increase velocity.

E.

Report daily progress to stakeholders.

Buy Now
Question # 32

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Buy Now
Question # 33

Which of the following are true about the Product Owner role? (Choose two.)

Options:

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Buy Now
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Feb 2, 2025
Questions: 250
PSM-I pdf

PSM-I PDF

$29.75  $84.99
PSM-I Engine

PSM-I Testing Engine

$33.25  $94.99
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$47.25  $134.99