An administrator needs to forecast infrastructure requirements for a new program and its associated applications. Prior to the projected start of the new program, all existing applications will be decommissioned.
How should the administrator perform this task?
An administrator is monitoring the Nutanix v5.15-based AOS cluster performance logs and notices that a SQL server VM is greatly exceeding its intended maximum IOPS. The administrator has confirmed that a QoS policy was previously created for the group of VMs this server is a member of.
What are two reasons that this VM would exceed its maximum configured IOPS from the QoS Policy? (Choose two.)
An administrator recently installed Prism Central to use categories, after having created categories and values, the administrator needs to apply these categories to multiple workloads.
How can the administrator easily perform this task?
An administrator needs to create and start five new VMs for a Data Analytics Project (OLAP). The VM Profile is as follows:
• vCPU:4
• vRAM: 64 GB
• vDisk: 1.5 TB
Each of the four nodes of the Nutanix cluster has the following:
• 24 vCPU. 20% overall usage
• 192 GB RAM, 60% overall usage
• 2xl920GBSSD
• 4x 2 TB HDD
At cluster level, there is a single RF2 container that is 30% utilized and has an extent store capacity of 13.5 TB.
Which component requires administrator attention?
Over the period of 2 to 3 weeks, a cluster displays the following:
•Periods where Warning Alerts of memory usage over 75% are asserted
•Periods where Critical Warnings of memory usage over 90% are asserted
•Periods of slow of frozen VDI desktops have caused work stoppage or slowdown
•VDI clones have periodically not powered up when called, causing work stoppage
Which steps should be used to prioritize the administrator’s troubleshooting efforts?