Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

ISEB-PM1 Exam Dumps - BCS Project & programme management and consultancy certifications Questions and Answers

Question # 74

Which of the following is an output of the Information Distribution Process?

Options:

A.

Project calendar

B.

Communication management plan

C.

Requested changes

D.

Communication requirement plan

E.

Organizational Process Assets Updates

Buy Now
Question # 75

If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?

Options:

A.

$0.2

B.

$5

C.

$44

D.

$66

Buy Now
Question # 76

How is quality control performed?

Options:

A.

By identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed.

C.

By ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Question # 77

Stakeholder analysis identifies what information and relates it to the purpose of the project?

Options:

A.

Requirements, influence, and functional department

B.

Interest, requirements, and functional role

C.

Requirements, expectations, and influence

D.

Interest, expectations, and influence

Buy Now
Question # 78

Total funding requirements and periodic funding requirements are derived from:

Options:

A.

funding limit reconciliation

B.

scope baseline

C.

activity cost estimates.

D.

cost baseline.

Buy Now
Question # 79

Within a matrix organization, dual reporting of team members is a risk for project success.

Who is responsible for managing this dual reporting relationship factor?

Options:

A.

Functional manager

B.

Project manager

C.

Functional manager supported by the project manager

D.

Project management office

Buy Now
Question # 80

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options:

A.

90 days

B.

100 days

C.

110 days

D.

660 days

Buy Now
Question # 81

Which type of analysis is used as a general management technique within the Plan Procurements Process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Question # 82

Giving a part of project work to a contractor is an example of:

Options:

A.

risk assumption

B.

risk assignment

C.

risk delegation

D.

risk deflection

E.

risk mitigation

Buy Now
Question # 83

Which contract type is typically used whenever the seller's performance period spans a considerable period of years?

Options:

A.

Fixed-Price-Incentive-Fee contracts (FPIF)

B.

Fixed Price with Economic Price Adjustment contracts (FP-EPA)

C.

Cost-Plus-Fixed-Fee contracts (CPFF)

D.

Time and Material contracts (T&M)

Buy Now
Exam Code: ISEB-PM1
Exam Name: BCS Foundation Certificate in IS Project Management
Last Update: Feb 24, 2025
Questions: 625
ISEB-PM1 pdf

ISEB-PM1 PDF

$25.5  $84.99
ISEB-PM1 Engine

ISEB-PM1 Testing Engine

$28.5  $94.99
ISEB-PM1 PDF + Engine

ISEB-PM1 PDF + Testing Engine

$40.5  $134.99