Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

ISEB-PM1 Exam Dumps - BCS Project & programme management and consultancy certifications Questions and Answers

Question # 24

Which of the following is CORRECT about quality improvements?

Options:

A.

They are a tool of Perform Quality Assurance and an output of Verify Scope.

B.

They require the preparation of change requests or the recommendation of corrective actions.

C.

They occur only through experience of the project manager, team, and sponsor.

D.

They are a product of cooperation between the customer and the project manager.

Buy Now
Question # 25

While reviewing project performance, the project manager determines that the schedule variance is -500.

What is the BEST thing to do?

Options:

A.

Let the sponsor know.

B.

Determine the cost variance.

C.

Look for activities that can be done in parallel.

D.

Move resources from the project to one that is not failing.

Buy Now
Question # 26

A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar time.

What is the FIRST thing you should do?

Options:

A.

Re-baseline the schedule to reflect the new date.

B.

Analyze the critical path activities for potential to fast track or crash the schedule.

C.

Document the lack of progress and associated issues to management.

D.

Identify activities that required more time than planned.

Buy Now
Question # 27

A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate.

Who has the PRIMARY responsibility to solve this problem?

Options:

A.

Project manager

B.

Senior management

C.

Project sponsor

D.

Manager of the project management office

Buy Now
Question # 28

A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response.

Which of the following is the BEST thing for the project manager to do?

Options:

A.

Document the new risks and continue the Plan Risk Responses process.

B.

Make sure the project work is better understood.

C.

Spend more time making sure the risk responses are clearly defined.

D.

Get more people involved in the Identify Risks process since risks have been missed.

Buy Now
Question # 29

When are deliverables accepted or not accepted?

Options:

A.

When the project is initiated.

B.

As an output of the scope verification process.

C.

When the project is closing.

D.

In the contract closure process.

Buy Now
Question # 30

Which describes how cost variances will be managed?

Options:

A.

Cost management plan

B.

Cost baseline

C.

Cost estimate

D.

Chart of accounts

Buy Now
Question # 31

Which of the following would be the MOST appropriate thing to do during the monitoring and controlling process group?

Options:

A.

Implement recognition and reward systems.

B.

Obtain sign-off of the product of the project.

C.

Issue performance reports.

D.

Keep everyone focused on completing the project to the charter.

Buy Now
Question # 32

You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented.

What type of risk is this called?

Options:

A.

Residual risk

B.

Mitigated risk

C.

Secondary risk

D.

Trigger risk

Buy Now
Question # 33

What quality control tool graphically represents how various elements of a system interrelate?

Options:

A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Buy Now
Exam Code: ISEB-PM1
Exam Name: BCS Foundation Certificate in IS Project Management
Last Update: Feb 24, 2025
Questions: 625
ISEB-PM1 pdf

ISEB-PM1 PDF

$25.5  $84.99
ISEB-PM1 Engine

ISEB-PM1 Testing Engine

$28.5  $94.99
ISEB-PM1 PDF + Engine

ISEB-PM1 PDF + Testing Engine

$40.5  $134.99