Professional Scrum with Kanban PSK-I Exam Dumps

Page: 4 / 4
Question 16

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

(choose the best answer)

Options:

A.

Throughput.

B.

Story points delivered.

C.

Cycle Time.

D.

Number of Product Backlog items finished in a Sprint.

Question 17

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

Options:

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Question 18

Which of these statements about Sprints and Kanban is NOT correct?

(choose the best answer)

Options:

A.

The Sprint is an example of a cadence.

B.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of an explicit policy for how a team is working.

Question 19

True or False: Little's Law is used to forecast a Scrum Team's output.

Options:

A.

True

B.

False

Page: 4 / 4
PSK-I Reviews Questions, Download Latest PSK-I Questions, Professional Scrum with Kanban PSK-I Exam Dumps,
Exam Code: PSK-I
Exam Name: Professional Scrum with Kanban (PSK 1) Exam
Last Update: Jan 22, 2025
Questions: 73
PSK-I pdf

PSK-I PDF

$29.75  $84.99
PSK-I Engine

PSK-I Testing Engine

$33.25  $94.99
PSK-I PDF + Engine

PSK-I PDF + Testing Engine

$47.25  $134.99