Question 44

Drafting a specification is important because these documents become embedded within the contract and therefore, are legally binding. Is this statement true?

Options:

A.

No, as the specification is separate to the contract and has no legal standing

B.

Yes, because all specifications must be approved by the organisation's board according to legislation

C.

No, because legally binding contracts only contain terms and conditions

D.

Yes, care needs to be taken because the specification should be part of the contract

Question 45

A buyer is using a framework agreement to purchase office furniture. The buyer invites the four suppliers listed on the framework to quote for the furniture; the winning bid is the lowest price. What would best describe this approach?

Options:

A.

Direct call-off

B.

Competitive tender

C.

Quotation exercise

D.

Mini competition

Page: 11 / 11
Exam Code: L3M4
Exam Name: Team Dynamics and Change
Last Update: Dec 22, 2024
Questions: 150
L3M4 pdf

L3M4 PDF

$25.5  $84.99
L3M4 Engine

L3M4 Testing Engine

$28.5  $94.99
L3M4 PDF + Engine

L3M4 PDF + Testing Engine

$40.5  $134.99