XI Corporation awards a contract for the building of a prototype critical to its introduction of a new product line. To protect itself against delays and unsatisfactory quality, which of the following is MOST appropriate for Xi's supply manager to require from the contractor?
A service provider has experienced diminished value and stagnant results within an important category. Which of the following is the BEST course of action the firm can take to improve the category strategy?
A software design firm has traditionally done most of its work in-house, including support services and distribution management. The firm is planning a large expansion, and is evaluating how the various departments can support It. The chief executive officer (CEO) recommends concentrating on core competencies to increase the firm's agility and emphasize what differentiates them from competitors. Which of the following is the BEST way supply management can support this recommendation?
A firm’s supply manager is asked by the engineering department to replace a chemical used in a majority of products made by the firm. The current chemical is Imported and has components that are highly regulated. Engineering wants to replace it with a chemical that uses non-hazardous domestic materials. This chemical would still have to be reported and customers would have to be notified of the change. Initial tests indicate that the new chemical is as effective as the old one. In this situation, which of the following should be the FIRST step taken by the supply manager?
A supply manager Is conducting financial analyses of bidders. The supply manager wants to select the supplier that is the most efficient in its use of assets. Based on the following information, which supplier should the supply manager choose?
A machine that costs $200,000 is expected to realize an annual savings of $35,000. What is the simple ROI for this piece of equipment?
XYZ, Inc. is negotiating with Supplier DEF for materials needed in manufacturing. The negotiations are moving slowly, primarily due to delays and postponements by the supplier. DEF has been the primary source for the material under negotiation, and while there are other potential sources, lead times would not make it feasible for XYZ to seek an alternative on such short notice. Which of the following tactics is DEF MOST likely employing?
CDE Inc. is a metal casting manufacturer that uses a supplier performance scorecard to measure key performance indicators (KPIs) across the business. CDE's supply manager wants Supplier Y to improve on a number of the measured KPIs. Which of the following is the BEST approach for the supply manager to take in order to achieve this objective?
A large manufacturing firm has offices across the country. The company wants to obtain the best price and reduce administrative costs associated with procuring office supplies. Which of the following would be BEST suited to the firm's needs?
JKL, Inc. solicits bids for the repair of a boiler used in its shoe factory. Supplier A submits a bid of $7000. The next lowest bid is $8,000, and the remaining bids are between $10,000 and $11,000. JKL awards the contract to Supplier A. However, before beginning repairs, Supplier A realizes it made a mistake and underestimated the repair work. Supplier A refuses to do the work, saying it would lose money. If JKL declines to increase the payment and claims that Supplier A breached the contract, the MOST likely result would be which of the following?