Question # 44

Telling a seller during negotiations that "This is our best and final offer" is a(n)

Options:

A.

strategic move that can shorten an otherwise lengthy negotiation, which should only be used when strong benchmarking supports the offer

B.

risky negotiating tactic that should be used with caution, and only if the buyer has a suitable alternative

C.

effective tactic that typically yields an optimum result

D.

tactic that should be avoided regardless of the circumstances, due to its potential harm to the client-supplier relationship

Buy Now
Question # 45

A supply manager is leading a negotiation team. This team will negotiate with several finalists supplying complex services. Prior to the negotiations, the supply manager briefs the team on strategies, roles and responsibilities. The team members seem to understand the importance of these factors, but shortly after the negotiations commence, several members begin to make mistakes such as arguing witF each other and failing to pay attention. Which of the following is the BEST course of action for the supply manager to take at this point?

Options:

A.

Call a caucus and reiterate the negotiation rules and their Importance In interactions with suppliers

B.

Remove the offending stakeholders from the negotiations, as they are not following the instructions

C.

End the negotiations and begin another round with different team members

D.

Contact the team members’ supervisors and express concern over the way they acted during the negotiations

Buy Now
Question # 46

A supply manager seeks bids on a new piece of capital equipment. The equipment is budgeted at $115,000. Three suppliers send in bids of $110,000, $114,000 and 5135,000. After receiving the bids, additional negotiations with the low bidder result in a final cost of $105,000. In this situation, what should the baseline value be for calculating cost avoidance?

Options:

A.

$114,000

B.

$135,000

C.

$110,000

D.

$115,000

Buy Now
Question # 47

A supply management department is asked to obtain lower prices from suppliers. Through its efforts, the department manages to achieve a 5% reduction in indirect spend categories. However, some stakeholders request more items, keeping total expenditures about the same despite lower per-item costs.

Which of the following will be the BEST long-term approach for supply management to improve upon this situation?

Options:

A.

Refrain from processing orders for additional items unless there is a compelling justification

B.

Report the problem to top management, citing the departments with the poorest records

C.

Work with leadership to implement a more effective demand management program

D.

Accept additional orders only if the requesting department has at least a 5% overall reduction in spend

Buy Now
Question # 48

A supply manager is planning a major sourcing event and wants to increase competition, especially by small and minority-owned businesses. The supply manager strives to maintain fairness with all suppliers. Which of the following is the BEST way to encourage diverse suppliers to participate?

Options:

A.

Apply a percentage decrease on unit costs during evaluation

B.

Expand advertising of bidding opportunities

C.

Adjust delivery requirements

D.

Modify contract terms and conditions

Buy Now
Question # 49

A buyer for DEF, Inc. has been exceeding spending authority on agreements with several new suppliers. Which of the following Is an accurate statement regarding DEF's liability in this situation?

Options:

A.

DEF is only liable for an amount equal to the buyer's actual authority level.

B.

DEF is fully liable for the agreements, as the buyer is an employee of the company.

C.

DEF is responsible for the agreements if the buyer exceeded actual authority, but the suppliers perceived the spend to be within apparent authority.

D.

DEF is responsible for the agreement if the buyer exceeded actual and apparent authority levels, but only for a value equal to the apparent authority amount.

Buy Now
Question # 50

DEF, Inc. wants to ensure adequate material supply for an emerging product with high quality specifications for the raw materials. Given this situation, which of the following would be the BEST course of action for DEF to take?

Options:

A.

Select an approved supplier and work collaboratively with it to meet the entirety of the organization's quality requirements

B.

Ensure a wide selection of suppliers are offered opportunities to submit bids

C.

Choose a supplier with a large infrastructure and high quality standards

D.

Select a preferred supplier to cover the bulk of the requirement and supplement the balance with qualified suppliers

Buy Now
Question # 51

A sourcing manager is asked by a stakeholder to purchase electronic signature software. To avoid additional license fees, the stakeholder wants an inclusive price covering all of the software's functionality. However, the budget available for the purchase is limited, and an all-inclusive package will drive up price. Given this situation, which of the following is MOST important for the stakeholder to provide before the sourcing manager contacts potential suppliers?

Options:

A.

The complete project timeline

B.

A list classifying software functions as either "must have" or "nice to have"

C.

An explanation of why the avoidance of additional license schedules is justified

D.

A complete list of software functionality

Buy Now
Question # 52

A product's labor content is $10 and its overhead is $12.50. The product sells for $36.50 per unit. Over the past year, supply management has reduced the product's cost of materials from $14 per unit to $12.

How much have supply management's efforts contributed to profit?

Options:

A.

$2.00

B.

$2.50

C.

$3.00

D.

$4.00

Buy Now
Question # 53

Separating processes such as ordering, receiving, and payment into different duties to be performed by different employees represents what aspect of internal controls?

Options:

A.

Risk assessment

B.

Control activities

C.

Work control

D.

Quality control

Buy Now
Exam Code: CORE
Exam Name: Supply Management Core Exam
Last Update: Feb 23, 2025
Questions: 312
CORE pdf

CORE PDF

$25.5  $84.99
CORE Engine

CORE Testing Engine

$28.5  $94.99
CORE PDF + Engine

CORE PDF + Testing Engine

$40.5  $134.99