Youare working on a project where the business partof the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''
You are managing the testing for a bank card project.The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lotof risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving
You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?
Which of the following is required to apply an experience-based testing approach''
Which of the following best describes the appraisal costs in the cost of quality'
You are working on a project that is having problems with regressions. Witheach release of software given to the test team. 50% of the defects found are actually regressions.To combat this you have decided to implement test automation.You have given your automation team the following goal
'Implement lest automation to automate 90% of the manual regression tests before the productrelease date.’’
Which of the following is likely an issue with this goal being defined as "SMART?