Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

AgilePM-Practitioner Exam Dumps - APMG-International AgilePM Questions and Answers

Question # 34

How should the Project Manager assist the electricians to deliver the wiring?

Options:

A.

Provide separate electricians' rooms so they can focus on their work.

B.

Hold a weekly meeting for electricians so they can report on progress.

C.

Encourage the Business Ambassador to be available to discuss location of electrical sockets.

D.

Produce a detailed design of all electrical socket locations, to be approved by the Technical Co-ordinator.

Buy Now
Question # 35

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.

B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.

C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.

D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.

Buy Now
Question # 36

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Buy Now
Question # 37

Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the

project in the Prioritised Requirements List?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Project Manager and Solution Development Team.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Buy Now
Question # 38

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Buy Now
Question # 39

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?

Options:

A.

The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.

B.

Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed.

C.

During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.

D.

The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.

E.

The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.

Buy Now
Question # 40

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to "temporarily weatherproof the roof" should NOT be set until Solution Development Timebox A.

Is this an appropriate approach to setting high-level acceptance criteria?

Options:

A.

Yes, because the Local Planning Authority Officer will set the acceptance criteria.

B.

Yes, because acceptance criteria are NOT set before the Timeboxed work is started.

C.

No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.

D.

No, because a Review Session should have been scheduled during Feasibility to enable the Solution Development Team to validate their understanding of the Local Planning Authority Officer's expectations.

Buy Now
Question # 41

Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?

Options:

A.

Is an external consultant.

B.

Has good leadership skills.

C.

Has experience of working with the company previously.

D.

Has a good, technical understanding of the work of the other professionals engaged in the project.

E.

Is an authority on local planning applications.

Buy Now
Question # 42

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Options:

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.

Buy Now
Question # 43

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

Options:

A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.

C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.

D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Feb 23, 2025
Questions: 134
AgilePM-Practitioner pdf

AgilePM-Practitioner PDF

$25.5  $84.99
AgilePM-Practitioner Engine

AgilePM-Practitioner Testing Engine

$28.5  $94.99
AgilePM-Practitioner PDF + Engine

AgilePM-Practitioner PDF + Testing Engine

$40.5  $134.99