Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being
planned in detail. Although Foundations was conducted at a high level, the
Prioritised Requirements List was baselined. Now the Solution Development
Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the
project in the Prioritised Requirements List?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to "temporarily weatherproof the roof" should NOT be set until Solution Development Timebox A.
Is this an appropriate approach to setting high-level acceptance criteria?
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?